Spacecraft Construction Status
check24.gifJan 06, 1998 Begin Spacecraft Assembly
check24.gifFeb 05, 1998 Spacecraft Electrical Power and Continunity
check24.gifFeb 05, 1998 Sample Return Capsule Deploy and Checkout
check24.gifMay 2, 1998 CIDA Electronics Installed
check24.gifMar 13, 1998 Deep Space Network Compatibility Test
check24.gifMay 18, 1998 Functional Bus Test
check24.gifMay 19, 1998 Sample Return Capsule Assembly and Test
check24.gifMay 21, 1998 CIDA Sensor Installed and Tested
check24.gifMay 28, 1998 Sample Return Capsule Integrated
check24.gifMay 28, 1998 Fold Up Bus (Initial)
check24.gifJun 24, 1998 Navigation Camera Test
check24.gifJun 25, 1998 Spacecraft Performance Test 1
check24.gifJun 28, 1998 Spacecraft Closed Up
check24.gifJun 29, 1998 Periscope Installation
check24.gifJun 30, 1998 Install Parachute in Sample Return Capsule
check24.gifJul 02, 1998 Solar Array Installation
check24.gifJul 11, 1998 Begin Tests in Multifunction Test Facility
check24.gifJul 15, 1998 Spin Balance Test
check24.gifJul 18, 1998 Weigh Spacecraft
check24.gifJul 18, 1998 Move to RAL Highbay (Reverberant Acoustics Laboratory)
check24.gifJul 19, 1998 Begin Pre-Environmental Performance Tests
check24.gifAug 02, 1998 Pre-Environmental Alignment Complete
check24.gifAug 05, 1998 SRC Deployment Test
check24.gifAug 07, 1998 Load IPA into Propellant Tank
check24.gifAug 11, 1998 Frequency Survey
check24.gifAug 14, 1998 Acoustic Test
check24.gifAug 19, 1998 Pyro Shock/Sep Tests
check24.gifAug 20, 1998Drain IPA
check24.gifAug 24, 1998 EMC/EMI Test
check24.gifAug 27, 1998 Solar Array Deployment Test
check24.gifSep 09, 1998 Payload Adapter Fixture (PAF) Fit Check
check24.gifSep 15, 1998 Install MLI and Prepare for Thermal Vacuum
check24.gifSep 24, 1998 Thermal Vacuum Test
check24.gifOct 1, 1998 Flight Aerogel Tray Set Delivered
check24.gifOct 2, 1998 Propulsion Leak Test
check24.gifOct 14, 1998 System Performance Test (SPT3)
check24.gifOct 14, 1998 Install Flight Aerogel
check24.gifOct 15, 1998 Fault Protection Test
check24.gifOct 21, 1998 Mass Properties/Spin Balance
check24.gifNov 11, 1998 Pack and Ship to Kennedy Space Center
check24.gifNov 12, 1998 Arrive at PHSF at Kennedy Space Center
check24.gifDec 11, 1998 Thermal Components Installed
check24.gifDec 21, 1998 System Performance Test (SPT4) at KSC
check24.gifJan 10, 1999 Final Solar Array Illumination Test
check24.gifJan 11, 1999 Closeout Solar Arrays
check24.gifJan 13, 1999 Install Solar Array Separation Bolts
check24.gifJan 18, 1999 Load Spacecraft Propellant and Test
check24.gifJan 18, 1999Load Final Flight Software
check24.gifJan 18, 1999Multilayer Insulation (MLI) Closeout
check24.gifJan 19, 1999Fianl torqueing solar array sep bolts
check24.gifJan 25, 1999Fianl Weighing of Spacecraft
check24.gifJan 26, 1999Mate STARDUST Spacecraft to 3rd Stage
check24.gifJan 28, 1999Erect Launch Vehicle
check24.gifFeb 07, 1999Launch Spacecraft