STARDUST Status Report
November 20, 1998
Ken
Atkins
STARDUST Project Manager
Assembly, Test, and Launch Operations (ATLO) activities: The principal ATLO
activities this week have been opening the spacecraft and installing
thermal tape, heaters and thermostats and installing the reworked (for
glass body diodes) solar array switching unit (SASU). All support equipment
was also checked out. The first week activities at Kennedy Space Center
(KSC) have been very efficient and smooth with work accomplished well inside
the scheduled timeline. KSC support has been outstanding.
Daily time-lapse movies are now being created of the launch preparations at
KSC: