Spacecraft Commissioning Continues
European Space Agency
March 24, 2004

Report for week 12 to 19 March

Since the last status report there have been two major areas of commissioning activity: for the first five days the focus was on the lander; followed later by the various plasma detection packages on the orbiter.

The Lander activities were all performed successfully and completed well within the scheduled time. This enabled the early execution of a number of activities initially planned for a later slot. Only one activity, the Lander MSS check, was postponed to allow re-definition of the procedure in view of the fact that the launch locks were released earlier than planned (on mission day 1).

In the last two days the Rosetta Plasma Consortium (RPC) commissioning activities started. The first day saw the successful activation and check out of all RPC instruments using the main power supply and data processing unit. During a repeat test using the redundant chain a sudden interruption in telemetry and drop in current consumption was detected. Investigations suggest a failure in the redundant power supply.

On the last day of the reporting period the spacecraft booms carrying the RPC MIP (Mutual Impedance Probe) and LAP (Langmuir Probe) instruments were successfully deployed using the primary systems. The instruments were active during the deployment and confirmed the successful operation via readings in their science telemetry. In order for further analysis to take place on the failure in the redundant power supply all remaining RPC activities have been postponed to a later date.

The table below shows a chronology of the main activities in the reporting period:

Mission Day Date DOY Main Activity

11 12/13.03.04 72/73 Lander Commissioning Pass 1

12 13/14.03.04 73/74 Lander Commissioning Pass 2

13 14/15.03.04 74/75 Lander Commissioning Pass 3

14 15/16.03.04 75/76 Lander Commissioning Pass 4

15 16/17.03.04 76/77 Lander Commissioning Pass 5

16 17/18.03.04 77/78 RPC Commissioning Pass 1

17 18/19.03.04 78/79 RPC Commissioning Pass 2 and boom deployment

At the end of the last New Norcia pass in the reporting period (DOY 079, 09:00) Rosetta was at 5.5 million km from the Earth. The return signal travel time was 36.8 seconds.

Future Activities
Payload commissioning will continue throughout March, April and May. During the coming week commissioning will commence on ROSINA, ALICE and VIRTIS.

News Archive Search  Go!
Show  results per page
 
 
Awards and Recognition   Solar System Exploration Roadmap   Contact Us   Site Map   Print This Page
NASA Official: Kristen Erickson
Advisory: Dr. James Green, Director of Planetary Science
Outreach Manager: Alice Wessen
Curator/Editor: Phil Davis
Science Writer: Autumn Burdick
Producer: Greg Baerg
Webmaster: David Martin
> NASA Science Mission Directorate
> Budgets, Strategic Plans and Accountability Reports
> Equal Employment Opportunity Data
   Posted Pursuant to the No Fear Act
> Information-Dissemination Policies and Inventories
> Freedom of Information Act
> Privacy Policy & Important Notices
> Inspector General Hotline
> Office of the Inspector General
> NASA Communications Policy
> USA.gov
> ExpectMore.gov
> NASA Advisory Council
> Open Government at NASA
Last Updated: 25 Mar 2004