12.09.04
STATUS REPORT: ELV-120904

EXPENDABLE LAUNCH VEHICLES STATUS REPORT

MISSION: Deep Impact
LAUNCH VEHICLE: Delta II 7925
LAUNCH PAD: Pad 17-B Cape Canaveral Air Force Station
LAUNCH DATE: Jan. 8, 2005
LAUNCH WINDOW: 1:39:50 and 2:19:12 p.m. EST instantaneous

In processing activities at the Astrotech Space Operations facility located near Kennedy Space Center, the high-gain antenna used for Deep Impact communications with Earth is being installed today. The solar array panels successfully completed an illumination test on Wednesday as a final check of their performance. On Friday, Dec. 10, the flight battery will be installed. The solar arrays stowed for flight on Dec. 13. Deep Impact will then be ready to begin preparations for fueling, which is scheduled to start on Dec. 16 and be completed on Dec. 19. Mating to the payload attach fitting and upper stage booster occurs Dec. 22 - 23.

The spacecraft is currently scheduled to be transported to Pad 17-B on Dec. 28 and mated to the Boeing Delta II rocket. The Flight Program Verification, the major integrated test with the Delta II, occurs on Dec. 30. The Delta II payload fairing will be installed around the Deep Impact spacecraft on Jan. 4.

NASA's Deep Impact spacecraft arrived in Florida on Oct. 23 to begin final preparations for launch. The spacecraft was shipped from Ball Aerospace & Technologies in Boulder, Colo., to Astrotech in Titusville.

Meanwhile, the stacking of the Boeing Delta II launch vehicle on Pad 17-B began on Nov. 22 with the hoisting of the first stage into the launcher. Hoisting of the nine strap-on solid rocket boosters, in sets of three, began with the first set on Nov. 23 and the second on Nov 29. The last set was installed on the vehicle on Dec. 1. The second stage was hoisted into position atop the first stage on Dec. 3. The payload fairing was hoisted and stowed in the mobile service tower on Dec. 6. The first power-on test occurred Dec. 7.

The next event is the vehicle guidance and control system check, which occurs on Dec. 13. The loading of liquid oxygen aboard the first stage for a leak check and a countdown launch team certification exercise is scheduled to occur on Dec. 14. The Flight Simulation, a plus count that exercises all of the systems on the vehicle as they will occur during powered flight, is scheduled for Dec. 15.

The overall Deep Impact mission management for this Discovery class program is conducted by the University of Maryland in College Park, Md. Deep Impact project management is handled by the Jet Propulsion Laboratory in Pasadena, Calif. The spacecraft was built for NASA by Ball Aerospace and Technologies Corporation.

News Archive Search  Go!
Show  results per page
 
 
Awards and Recognition   Solar System Exploration Roadmap   Contact Us   Site Map   Print This Page
NASA Official: Kristen Erickson
Advisory: Dr. James Green, Director of Planetary Science
Outreach Manager: Alice Wessen
Curator/Editor: Phil Davis
Science Writer: Autumn Burdick
Producer: Greg Baerg
Webmaster: David Martin
> NASA Science Mission Directorate
> Budgets, Strategic Plans and Accountability Reports
> Equal Employment Opportunity Data
   Posted Pursuant to the No Fear Act
> Information-Dissemination Policies and Inventories
> Freedom of Information Act
> Privacy Policy & Important Notices
> Inspector General Hotline
> Office of the Inspector General
> NASA Communications Policy
> USA.gov
> ExpectMore.gov
> NASA Advisory Council
> Open Government at NASA
Last Updated: 29 Dec 2004